HofmannCLASS 4 ATL MOT BAY Installation at Saxon Bridge Automotive


 Saxon Bridge Automotive in Wolverton, Milton Keynes already have a thriving business selling quality second hand vehicles, servicing and repairs and Practical vehcile hire,  they where spending a lot of money on out sourcing M.o.T work to other garages and decided that it would make good business sense to have their own onsite M.o.T bay.
 After the initial enquiry from Saxon Bridge we then organised to have a representative from Hofmann to meet us onsite to measure up the building and space that the bay would be situated in and design site drawings for the garage to be able to submit to VOSA for their application, working closely with Mark (workshop manager for Saxon bridge) we assisted him with the necessary information to get the application forms filled out and sent off. 

 Once Saxon Bridge had recieved confirmation from VOSA of Agreement in Principle, the order was placed for the HOFMANN CLASS 4 ATL MOT PACKAGE and work got under way to organise installation, we put Saxon Bridge in contact with an experienced builder in M.o.T bay ground work, organised site meetings with their electrician and organised dates for the ground work to be started and completed and the installation date of the Hofmann equipment.

Site meeting with electician Equipment arriving on site

The day prior to the start of the ground work, the floor was marked out ready for the builder.

 Marking out bay Marking out bay 2 Marking bay 3 Bay marked out

 

Tuesday 13th December 2011 saw the start of the ground work.
Cutting outline Cutting 

 Breaking up concreate Breaking up concreate 

Digging out hole Digging hole

Once the hole was dug and all of the debris was removed work began on costructing the frames for pouring the first stage of concrete.
framework Framework  concrete

While the concrete pad for the ramp was drying, work started on digging out the hole for the brake tester.
brake dig out Checking measurements Frame for brake tester

By Friday 16th December 2011 final preperations were made for the concrete to set ready for installation to start on monday morning.
   

 

The morning of Monday 19th December 2011 work started on installing the HOFMANN CLASS 4 ATL BAY equipment, representitives from Hofmann along with us where onsite to oversee the installation.
locating brake tester  

constructing lift                

 

Final construction, adjusments and tesings where completed and by approx 3pm on Tuesday 20th December work had been completed, the engineers had cleared away tools and equipment, cleaned away any rubbish and left Saxon Bridge Automotive with a nice new CLASS 4 ATL bay ready to go.
  Weight calibration seen through mirror

Final product ready for floor painting Ready to go

 


Saxonbridge.com


 

PD Motors

Hofmann MTF3000

*click on image to be taken to product page

Hofmann MTF3000 2 post lift Installed at PD Motors in Leighton Buzzard